Robot Integration Projects: Specification, Acceptance, Liability
A robot cell is rarely bought off the shelf. A systems integrator designs, builds and commissions it. How to write the specification, test the result and settle who answers for what.

Buying a robot is the easy part. Making it pick the right part, at the right speed, next to the right machine and without putting anyone at risk is a project. Most companies hand that project to a systems integrator. This is a firm that designs the cell, sources or builds its components, writes the software and commissions it on site.
The integrator sits between the buyer, the robot maker and often several other suppliers. That position makes it the key to success and a frequent source of disputes. When a cell runs too slowly or fails with a new part variant, the first question is often who promised what.
This article looks at the integrator's role through three stages: the specification at the start, the acceptance tests at the end and the contract that defines responsibility in between.
What an integrator actually does
A robot arm on its own does nothing useful. The integrator adds the gripper or tool, the part feeding and fixtures, the sensors, the safety equipment and the control logic that ties the cell to the rest of the plant. It writes the robot program and often the program for the programmable logic controller, or PLC, that coordinates everything.
Typical work packages include:
- Concept and layout, including simulations of reach and cycle time.
- Selection of robot, gripper, vision system and other components.
- Safety concept and risk assessment for the whole cell.
- Mechanical and electrical design, build and wiring.
- Robot and PLC programming, including interfaces to existing machines.
- Testing, installation, commissioning, documentation and operator training.
In the EU, the party that assembles components into a complete machine usually takes on the duties of a manufacturer under machinery rules. These include the risk assessment, the technical file and the CE marking. Often that party is the integrator, but contracts sometimes assign the role differently. It should never be left unclear.
The specification sets the frame
Many troubled robot projects can be traced to a vague start. A buyer asks for a cell that loads a machine, and the integrator quotes a cell that loads a machine. Only later does it emerge that there are forty part variants, that some arrive oily and that the cycle time must match the fastest machine in the line.
The buyer's requirements specification should describe the task, not the solution. It covers the parts, with drawings, weights, tolerances and real samples. It states the required output per shift, the variants and how often they change, the existing machines and interfaces, the available space and the conditions on the floor. In German-speaking countries this document is known as the Lastenheft.
The integrator answers with a functional specification that explains how the cell will meet each requirement. Comparing the two documents line by line is tedious. It is also the most useful single step in the project. Every gap found here costs far less than one found during commissioning.
Every requirement left out of the specification comes back later as a change order.
Acceptance in two stages
Acceptance is where promises meet measurements. Most projects use two tests. The factory acceptance test, or FAT, takes place at the integrator's workshop before shipment. The buyer's team watches the cell run with real parts and checks the agreed functions, the safety devices and the documentation.
The site acceptance test, or SAT, follows installation in the plant, with the real machines, network and operators. Many problems only appear here. A conveyor delivers parts at a slightly different angle, a machine signal has unexpected timing, or light from a window confuses a camera.
Both tests need criteria agreed in writing beforehand. Useful ones are cycle time over a defined run, the share of successful picks or good parts, the handling of each variant, recovery after typical faults and the time needed for a changeover. A short demo with hand-picked parts proves little. A run over one or more full shifts says much more about daily performance.
Who answers for what
The contract should spell out responsibility where it usually blurs. Safety is one such area: who carries out the risk assessment, who signs the declaration of conformity and who must approve later changes. Interfaces are another. If the cell talks to a machine from another supplier, someone must own the interface definition and its tests.
Warranty and performance terms need care. A warranty that covers parts but not cycle time leaves the buyer exposed. Changes during the project should follow a written process with price and schedule effects. Informal requests made on the shop floor are a common source of conflict.
Software ownership is often forgotten. The buyer should receive the current robot and PLC programs, backups and documentation, with the right to modify them or pass them to another service provider. Without that, the plant depends on one integrator for every small change, for as long as the cell runs.
The buyer's share of the work
Integrators depend on their customers more than contracts suggest. They need accurate part data and samples early, quick decisions when options arise and access to the plant for installation. Delays on the buyer's side push the schedule just as surely as delays in the workshop.
The buyer also needs people who will own the cell after handover. Operators and maintenance staff should take part in testing and training rather than meeting the robot on the first production day. A cell that only the integrator understands will be expensive to keep running.
Choosing and keeping a good partner
When comparing integrators, look at similar cells they have built, not only at brochures. Ask to speak with past customers about how problems were handled after handover. Check whether the firm has capacity for service visits in your region and how quickly it responds to faults.
Many companies that run several robot cells end up working with a small number of integrators over many years. Those relationships work best when both sides keep the habits of the first project: precise requirements, measurable acceptance and clear responsibility.
Questions and answers
What is a robot systems integrator?
It is a company that combines a robot with grippers, sensors, safety equipment and controls into a complete, working cell. It usually handles design, programming, installation and commissioning. Robot makers often rely on integrators to deliver their machines for specific applications.
What should a requirements specification for a robot cell include?
It should describe the parts, variants, volumes, required cycle time, existing machines and interfaces, available space and conditions on the floor. Real part samples and drawings help the integrator design for reality. The document should describe the task rather than prescribe the technical solution.
What is the difference between FAT and SAT?
The factory acceptance test takes place at the integrator's site before delivery and checks the cell against the agreed functions. The site acceptance test follows installation in the plant and checks performance under real conditions. Both should use criteria agreed in writing beforehand.
Who is responsible for the CE marking of a robot cell?
In the EU, the party that assembles the components into a complete machine generally takes on the manufacturer's duties, including CE marking. That is often the integrator, but the contract can assign the role differently. What matters is settling it clearly before work starts.
Should we receive the source code of the robot programs?
Yes, in most cases. Access to the current robot and PLC programs and their documentation lets you make changes, recover after failures and switch service providers if needed. Agree on this in the contract, including how updates are handed over.